Joint flood protection system development on the right bank of Crisul Repede river in the cross-border area
Acronym:
CRISULHURO
Call:
HURO/1101
Priority:
Priority 1
Action:
1.3.2. Water management
Registration No.
HURO/1101/075/1.3.2
Total Project budget:
600 000,00 €
Total ERDF awarded:
510 000,00 €
Project start date:
01 January 2013
Project end date:
31 December 2014
Project status:
Finalized
The aim the project is to enhance the flood safety of the flood-control system on the right bank of Crisul Repede. For this two dike-reeve\'s plants in bad state will be restored on both border sides, the Crisul Repede hydrographical station on the state border will be restored; on the Romanian side the dike crown stabilization at the section of the dike Santion stone mine and Tarian dike-reeve\'s house will be implemented. The main professional activity of the project is to restore the out-of-date establishments in the border area; this activity includes as follows: - restoration of the dike-reeve\'s houses and its outbuildings in Körösszakál, - restoration of the automatic water gauge in the storing profile and IT improvement (Hungary) - restoration of the dike-reeve\'s house and its outbuildings in Tobolu (Romania) - restoration of the dike-reeve\'s house and its outbuildings in Tarian (Romania) - stabilization of the dike crown of the dike on the right bank of Crisul Repede in the section between the stone mine in Santion and the dike-reeve\'s house in Tarian The direct target group is formed by the specialists of the project partners. Among the project results: 4 dike-reeve\'s plants restored 1 joint monitoring system developed, 1 automated water gauge restored.
Partnership
ERDF awarded/ Lead Partner
Tiszántúli Vízügyi Igazgatóság
Hungary, Hajdú-Bihar, 4025 Debrecen, Hatvan u. 8-10.
255 000,00 €
ERDF awarded/ Project Partner 1
Water Basin Administration Crisuri
Romania, Bihor, 410125 Oradea, 35 no. Ion Bogdan Street